When a project manager approaches the end of their company’s big project, the company’s organizational structure, objective and Strategies have changed. What should the project manager take from the following methods?
A、Speak with the line one manager to ensure the whole resources should continue to complete the task which assigned before.
B、Check if there is budget available to continue the project following the master schedule.
C、Disregard the change in goals and strategies and continue to run the end.
D、Inquire with the project sponsor as to whether or not the project still fits the company’s Strategies.
10年專(zhuān)注信管,信管教育專(zhuān)注者,信管網(wǎng)優(yōu)勢(shì)
免費(fèi)試聽(tīng)信管網(wǎng)信息系統(tǒng)項(xiàng)目管理師課程
全國(guó)前50名高分學(xué)員訪(fǎng)談:董麗(174)、李思...
信息系統(tǒng)項(xiàng)目管理師高端班培訓(xùn)課程
信管老師100小時(shí)直播課程
軟考報(bào)名專(zhuān)題(報(bào)名時(shí)間、入口等)
中級(jí)系統(tǒng)集成項(xiàng)目管理工程師通關(guān)課程
系統(tǒng)規(guī)劃與管理師課程(考試介紹與題型分析)
軟題庫(kù):軟考在線(xiàn)題庫(kù)、支持手機(jī)答題