A project is in progress and the project manager is working with the quality assurance department to improve stakeholders' confidence that the project will satisfy the quality standards. Before they can begin this process, which of the following do they need to have?
A、Quality problems
B、Results of process Analysis
C、Quality audits
D、Quality management plan