国产欧美精品一区aⅴ影院,中文字幕福利,亚洲精品在线免费,www.综合色,国产精品正在播放 ,国产色手机在线观看播放,国产精品短视频

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱(chēng) 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

After reviewing the monthly project performance report, the project manager, when monitoring & controlling risks, identifies the need to implement a contingency plan. What does the project manager need to do?
A、Change the project work breakdown structure to accommodate the implementation of the contingency plan.
B、Raise a change request to the project.
C、Re-baseline the project so that the contingency plan can be executed.
D、Raise an issue and escalate to the senior manager.


相關(guān)試題

推薦文章